Chapter 4 - Compliance with the Code

Non-Compliance Procedures

In case of non-compliance with any of the technical provisions in this Grid Code, CEB shall inform the owner in writing of the discrepancies. The MSDG owner shall have 90 days to rectify the discrepancies.

Failing to do that, CEB shall be entitled to disconnect the MSDG installation.

Immediate Disconnection

CEB shall be entitled to disconnect the MSDG facility without prior notification if the installation conditions are harmful or creates unavoidable risks for the safety.

Liability

CEB shall not be responsible for any damage if such disconnection requires the disconnection of other loads associated or connected to the same connection as the MSDG.

Reconnection Requirements

Reconnection of the MSDG shall require that CEB certifies that the installation complies with this Grid Code. Fees applicable shall be the same as for reconnection fees.