Annex 3: CEB Fees

Interconnection facility and cost

The MSDG will be connected to CEB 22kV network through a High Voltage switchgear and metered on the high-voltage side.

In addition, the applicant shall bear fees for processing applications and preparation of cost estimate for network construction or modification. The value of each of the listed fees will be set by the CEB in specific bylaws and published on the CEB website.

Applicable Fees

Some of the fees that may be applicable are as follows:

  • Processing fee
  • Connection Fee
  • Engineering Review / Distribution Study: Preparation of estimate for network modification by the relevant CEB District section.
  • Revision of Estimate
Note: Applicants are advised to consult the CEB website for the latest fees.

Network construction / modification

The cost for network construction or modification will be determined after carrying out the engineering review.